Construction is progressing at Springfield Phase 2B, part of the wider Springfield Village development in Wandsworth. Barratt London is delivering 220 new homes for Wandle Housing Association, providing a mix of affordable rent and shared ownership homes. We are supporting Wandle as Quantity Surveyor, Project Manager and Clerk of Works, representing the client’s interests through construction and handover.
Site Progress
Block B, which is made up of four sub-blocks, is now well out of the ground. All level 3 precast planks are complete to Blocks B3 and B4, while blockwork and brickwork are progressing at level 2 on Blocks B1 and B2. The perimeter scaffold is being raised in step with the superstructure.
Windows have been installed to the ground and first floors, and M&E distribution is under way on these levels. LV and secondary underground supplies have been installed to the ground floor riser with jointing complete, and permanent road formation is in progress across the site. The district heating connection has also been completed, and no gas connection is required on site. Water, power and BT connections are being progressed, with BT service ducts currently being installed. A number of items raised through the Considerate Constructors Scheme have also been addressed and closed out, and arrangements are being made for show flats so that prospective shared ownership buyers can see the finished product.
Preparing for Handover
Alongside the works on site, the project team is laying the groundwork for a smooth handover. All collateral warranties have now been signed and accepted by Wandle, and the client and contractor teams are reviewing kitchen layouts, finishes and material selections together. A handover tracker is being developed so that Wandle has a complete record of what has been installed in every home, and a home user guide template is being refined to reflect the needs of residents. Planning is also moving forward, with wording agreed for several pre-occupation conditions and non-material amendments being prepared to refine the appearance of the buildings.
Our Role
As Quantity Surveyor, we are reviewing costs and variations on Wandle’s behalf, including proposals for additional items such as blinds to rented and shared ownership homes. As Project Manager, we chair the monthly progress meetings, track actions across the client and Barratt London teams, and lead the specification review for the rent and shared ownership homes. As Clerk of Works, we carry out regular inspections to ensure that works are being delivered to the required standard and in accordance with the specification, reporting any defects to the project team so that they can be put right before they are covered up by following trades. This close involvement means that Wandle can be confident the homes it receives meet its requirements, and that any changes are captured and agreed in good time. We look forward to sharing further updates as Block B moves towards being watertight.